March 14, 2003

 

 

Anita Masters

Tennessee Valley Authority

1101 Market Street, MR 2T

Chattanooga, TN  37402

 

Submitted Via Email

 

RE:  Comments on the draft Environmental Assessment of the “Aspen Grove-Bingham 161-kV Transmission Line, Williamson County, TN

 

Dear Anita Masters:

 

          This letter comprises the comments of the Harpeth River Watershed Association on the draft EA for the proposed 161-kV TVA transmission line to connect Aspen Grove substation to a proposed Bingham substation.  Our organization has been working with TVA and Middle Tennessee Electric Membership Corporation (MTEMC) since mid-2001 on this proposed project.   The HRWA first communicated our concerns regarding the proposed route’s potentially significant impact on water quality in July 2001 not long after this route became a working proposal from TVA.  Our 4-page comments are in Appendix I of the draft EA.

 

Since then, we have worked with the Heritage Foundation, the Southern Alliance for Clean Energy, the city of Franklin, Williamson County, landowners, Southern Land Company, and others on this proposed transmission line.  Two key components of this collaborative effort in 2001 were to work with Synapse Energy Economics to conduct a third-party independent review of TVA’s analysis and a study of the energy efficiency potential for the county.  These two studies will be addressed further below.  Since various entities that we have been working with will be submitting significant comments on this draft EA based on their areas of expertise, we will focus our comments here on the proposal’s effect on water quality and the inability for the river systems being affected to be able to meet state water quality standards should this project be completed as proposed.  Attached to this comment is the resolution of the board of the HWRA dated February 20, 2003 (Attachment 1) that covers all our concerns and the organization’s position opposing this transmission line proposal.

 

I.  Comments on Need and the Alternatives

 

With the growth in the Franklin area, electrical demand has increased.  Since the 1999 One Owner Study prepared by MTEMC, they have described in Appendix I several projects they have completed and are planning to do to upgrade their current distribution system in the area.  What the HRWA fundamentally challenges in not the need to serve electrical demand growth, but that this proposal of a transmission line along option B and a substation in Bingham is the most appropriate means to address it.  This motivated the study by Synapse Energy Economics in late 2001 to provide an independent analysis of this proposed transmission line following procedures used for other utilities that must meet FERC requirements to which TVA is exempt.  Though both MTEMC and TVA provided material, the information provided did not justify the need for new transmission lines and did not demonstrate that energy efficiency alternatives had been considered (see Attachment 2).

 

The Bingham Service Area and Load Growth:   The Draft EA does not adequately define the Bingham service area.  According to a map provided to us by MTEMC during the Synapse Energy Economics analysis process, the Bingham service area is practically all rural.  It includes a portion of western Franklin that is in the city’s Urban Growth boundary, but this is only about 15% of the geographic area.   Load growth for the Bingham service area will almost all be in this small area close to Franklin, within the city’s urban growth boundary, and not out in the rural area of the county where the Bingham substation is proposed to go.  Though SR 840 is proposed to come across at the southern end of the service area on the map, there will not be large subdivisions or office parks as a result since the county zoning oridnances and plan do not permit this type of development.  As a result, the community concerns are that the load needs are much closer to Franklin and not in the heart of this rural area of the county around the proposed Bingham substation location. 

 

          Energy Efficiency Alternatives:  Though the draft EA briefly describes TVA’s current energy efficiency programs, these are all voluntary as are those of MTEMC.  This EA is not adequately considering the contribution that efficiency can make to addressing load growth, distribution power generation, and other options that could be put in place immediately and over time.  This EA is based solely on electrical transmission, distribution, and system upgrades, not on any demand side management.   Synapse Energy Economics references that the US Government Accounting Office completed a study of TVA’s demand side management and found them lacking relative to other utilities (Attachment 2). 

 

          Synapse Energy Economics also conducted an analysis of the energy efficiency potential in Williamson County based on southeastern regional studies (Attachment 3).  The best opportunity to maximize efficiency opportunities is during new construction.  With the growth in the greater Franklin area, it is a great opportunity for MTEMC to address its system needs with energy efficiency.  This has not been done.  The analysis found that if only a portion of the cost-effective and technically available efficiency options were done that by 2010 electricity demand in the county could be reduced 13% which amounts to 274 GWh of electricity not needed.  This compares to orders of magnitude smaller 84 MWh projected need for the Bingham service area in the EA.  Also, this would result in net energy cost savings of $4.6 million a year! 

 

          Even though this study could not be very specific to Williamson County because of the lack of county specific data available to Synapse, the electrical needs in this region can be addressed with a combination of energy efficiency and infrastructure improvements that would reduce the cost to rate payers and enable the important cultural, environmental, historic, and aesthetic values of this region to be maintained.  The HRWA, SACE, Southern Land Company and the city of Franklin have expressed interest to TVA and MTEMC, and there has been a meeting to initiate an energy efficiency pilot.  Though TVA has not come back to present a package that was promised in December 2002, the community is ready to work with TVA and MTEMC to address load growth with demand side management.

 

Other Alternative configurations for transmission lines and substations:  As described in our joint comments to TVA on October 28, 2002 that are in the Appendix II of the draft EA, the overall nature of the transmission and distribution system plans by TVA and MTEMC has been unclear and conflicting.  From prior materials both MTEMC and TVA have produced, there clearly has been an intent that this transmission line is a piece of a larger project to make a connection to the Davidson Substation and bring a third feed to the county.  If this is so, though recently TVA correspondence has denied that any other transmission lines are planned while MTEMC staff are certainly planning on it, then all this infrastructure proposed to address load growth and reliability must been considered together and not piecemeal which is not allowed by NEPA  (see the October 28, 2002 comments).

 

Option A is viable and there appears to be time:  With the Bingham substation in its proposed location and option B for the TVA line as proposed, then the logical next project appears to be to build the TVA line connection along Option A back up to the Davidson Substation to make the 161-kV loop and get the third feed into the county.   The draft EA notes that this option is not timely because of the risk that the National Park Service may not permit the expansion of the existing minimal crossing of the Natchez Trace Parkway.  However, this option had the most support from the community, has the least impact on water courses, historic and cultural resources, and follows existing right-of-way.  It clearly is a viable option for a third feed into the county if this is necessary.  It is unsettling to think that TVA believes Option B is preferred because it does not have an entity, such as the National Park Service, along this Option B corridor that could deny it permission. 

 

It appears that the sense of urgency to relieve the Aspen Grove substation is driving the choice of Option B.  Yet, according to Appendix I, page 2, if tie ins are made between existing substations, then the existing system can spread the load and Aspen Grove will not reach capacity in 2004 as in the chart (which is based on no tie ins).  Instead Aspen Grove will not reach capacity until 2006 or even as late as 2010 because MTEMC is actively upgrading its system.

 

          It is also worth noting that though the costs in the 1999 One Owner study would need to be updated, at that time the alternative to do distribution system upgrades versus a new substation and a TVA line were almost identical in total costs.  Distribution system upgrades were estimated at $11.3 million, and building the Bingham substation was estimated at $5.3 million.  When the cost of the TVA line that has been estimated at $5.9 million is added, there is really no difference in total cost.  What is different is MTEMC only needs to spend half what it would if it did all system upgrades.   So, the proposal for a TVA line is not a cost savings to the rate payer.

 

          Alternatives to Option B and a planning process:  There are clearly alternatives to running the proposed transmission line along Option B, then building another transmission line along Option A.  The important next step would be for TVA to work with this community to pilot a more meaningful, engaged transmission planning process.  We would suggest that TVA look into using the transmission planning process similar to the one recently developed by a similar entity, Bonneville Power Administration.  Through this process, which includes energy efficiency, TVA and MTEMC would be able to define an infrastructure system with the community and avoid delays as has been experienced with this proposal. 

 

          We believe that there are some more appropriate options that Option B.  Though the HRWA does not endorse any of these, we would be willing to work as part of a planning process with TVA and MTEMC on considering these and others.   These below do not include energy efficiency and load distribution options that are described in the comments submitted by SACE.  For example:

 

  • Consider building the TVA line on Option A to the proposed Bingham substation now, and run distribution lines from Bingham back to the high growth area of West Franklin.  Distribution lines are generally much less intrusive that the monopoles proposed for the TVA line and would fit into the historic landscape of the surrounding area.  Nonetheless, routes and poles would need to be agreed on with local input.  This option ties with third one below if a 161-kV loop is needed.

 

  • Consider building a new substation along the Option B corridor much closer to Franklin versus the proposed Bingham location.  This location would be somewhere along the Mack Hatcher corridor and would avoid a line through the West Harpeth river system, most of the proposed Harpeth River Valley historic district, most of the historic properties, and the 96W gateway viewshed into Franklin.

 

  • Consider making a 161 k-V loop by using Option A to a Bingham substation, then continuing south along the same Maury-Davidson 500 kV Line and coming across the short distance in the southern part of the county to the Maury-Radnor 161 kV line.  This route between the two lines could follow the SR 840 right-of-way. 

 

II.   Comments on Environmental Consequences and Mitigation:

 

The HRWA is opposed to using Option B.  It appears that any of the proposed routes in Option B will have significant effects to water quality, historic and cultural resources, and viewsheds of importance to the county and city in their planning.  The Bingham substation location makes it impossible to site a route that doesn’t significantly adversely impact historic, scenic, archeological or cultural resources or contribute to degradation of river systems.  As outlined in the section above, the HRWA believes that there are other options to this proposed line in this corridor.

 

Preferred route of Option B has the most river crossings and a lengthy floodplain corridor:

 

The HRWA already submitted extensive comments regarding the negative effects on water quality and riparian corridors from the proposed route (see Appendix II).  These here are additional comments.  It appears that when TVA was considering which of Options A-D to pursue, the effect on river systems was not even considered.  The draft EA does not even list the need to cross the Harpeth and West Harpeth as siting constraints for Option B (p. 16).  Not only does the proposed route have the maximum river crossings, the need to construct access roads is a vital issue with the proposed route going along the West Harpeth riparian corridor and along the main Harpeth corridor.

 

          To add reference data to our comments on July 2001, I have attached the summary report of the Volunteer Visual Stream Assessment report that was conducted in the Harpeth on the state designated impaired streams with funds from the TN Department of Agriculture’s NonPoint Source Program (Attachment 4).  There are a number of sites surveyed with poor riparian habitat and unstable banks that are under transmission and distribution lines.  Here is an image on the West Harpeth where a 500-kV line crosses just south of the proposed multiple crossings for this proposed 161-kV line.  Active bank erosion and no bank vegetation is a common sight for line crossings throughout the watershed, and are active sites of erosion.

 

Figure 1:  Maury-Davidson 500-kV transmission line crossing the West Harpeth near Old Boyd Mill and Blazer Road, Williamson County  (looking south).  The bare bank is approximately 5 feet high. © Walton, HRWA.

 

In addition, the final technical report is complete on the two year sediment study on the Harpeth.  This study has helped quantify the amount of sediment loss in the upper half the Harpeth and indicates specific streams with erosion problems.  There were five study sites on the West Harpeth (see Attachment 5).  Data from Table 4-1 of this sediment study shows that the site at the confluence of the West Harpeth and main Harpeth is possibly as much as 5 times more turbid that the site upstream at Leipers Fork, a tributary on the West Harpeth.   Many actively eroding banks are a source of this sediment load based on the Visual Stream Assessment survey, and the preferred TVA route will add 10 more exposed streambanks.  There was also a sediment study site on the main Harpeth downstream of the proposed TVA crossings and before the confluence of the West Harpeth that documented high turbidity.

 

The draft EA states on page 37 that the various alternative routes are not different in their affect on water quality.  This is hard to justify when alternative C would eliminate many West Harpeth River crossings though this segment runs along scenic Old Boyd Mill Pike.  River crossings would also be minimized if the TVA route followed the Mack Hatcher right-of-way.  The various alternative routes are not interchangeable in terms of their impacts to water quality and stream integrity.  To minimize the impact of the proposed transmission line on the river system, the route would need to follow the Mack Hatcher right-of-way, and run out 96W until the West Harpeth bridge before heading south to the proposed substation. 

 

On the visual impacts of the line, the draft EA is incorrect in assuming that the 5 crossings of the West Harpeth would not affect the view.  Many people in the area enjoy canoeing this section of the West Harpeth because it is easy to gain access not far south of the proposed substation and egress where the West Harpeth joins the main Harpeth.  Multiple line crossings and canopy openings will definitely affect the view from the river.

 

Mitigation proposed is not adequate

 

We are glad to see that the draft EA gave consideration to how to mitigate for the numerous river crossings.  However, we believe that the mitigation offered in draft EA in section 4.4 on Aquatic Ecology, in Appendices IV-VII, and elsewhere is not sufficient to make the determination that the proposed route with the most river crossings would have insignificant impacts.  The mitigation proposed would involve TVA resource stewardship staff consulting on the construction design and making recommendations for native plantings and other means to provide bank stabilization.  But, it appears that all the project control is with the Transmission Construction department.  The reality is that all the mitigation and oversight is within TVA and that even with best laid plans, proper implementation is the key.  If there is not very active oversight and involvement that includes outside and locally based expertise, during design, construction, re-vegetation, and active efforts with land owners, it is highly unlikely that this proposed route will end up with 18 stable stream banks with good vegetation stream buffers. 

 

The other mitigation mentioned in Appendix VI was that all intermittent and perennial water courses be designated as Level B, Protection of Important Permanent Streams.  The two additional requirements this involves from the standard level of protection is to reduce tree cutting to just those that are considered dangerous to the infrastructure, and that proposed crossings will be discussed in advance with TVA resources Stewardship staff and require on-site planning.  This Level B designation could help, but it will not amount to much if the contractor does not actually follows through with the plans.

 

          Predominantly the draft EA give little indication that the construction and vegetation management of the line corridor will be anything other than current practices.  Yet, it is precisely current practices that are the reason for water quality problems at line crossings. The mitigation language refers to the Guide by Muncy, “BMPs for TVA Transmission Line Construction and Maintenance.”  It is great to see that TVA has a guide, but it is more important that the contractor is very qualified and has a good track record.  Giving a contractor this manual is no guarantee for appropriate work.

 

Though the guide was updated in 1999, there is little if any mention of use of native plantings or low growing shrubs in the stream management zone.  Several figures do not depict adequate erosion control plans such as Figure 2 for access roads.  This guide only refers to stream crossings for equipment of banks up to 5 feet high.  This is lower than the banks on the main Harpeth.  Also a major weakness with the initial reseeding of bare soil after construction is lack of follow-up.  This is where contractors tend to cut corners. 

 

Vegetation re-clearing plans are described in the draft EA as being the typical regime of mechanical mowing and herbicide use that is intended to maintain not much other than grass.  The missed opportunity and problems with these re-clearing plans are an issue in TVA territory as noted by the work of the Public Lands Subcommittee of the RRSC to establish a policy on “TVA Transmission Line Rights-of-Way Maintenance Policies and Practices.”  This policy is intended to encourage more attention to existing re-clearing and opportunities to work with land owners to use native species, improve habitat integrity, and consider wildlife benefits in the rights-of-way.  The draft EA noted the presence of invasive species in this region.  So there is an opportunity with the vegetation plans to use native plants that not only need minimal management (re-clearing), but would also help with restoration of terrestrial and aquatic habitat quality. 

 

Another example of lack of effort to move beyond current “business-as- usual” for line construction and corridor management is that the restoration of all disturbed sites is simply to establish grass cover.  There are many options that would be appropriate to use and it would also mean that the construction contractor is not likely to be the best to do the restoration plan.  In addition, it would be best to avoid burning the cleared vegetation that is a typical practice as described in the draft EA.  This cleared vegetation can be converted to mulch and used an effective sediment control barrier.  Mulch is also used as an erosion mitigation measure for cover for a bare site. 

 

          Mitigation for the effects of so many river crossings and running along the West Harpeth riparian corridor will require a combination of actually re-aligning the route to reduce crossings and a real commitment of additional funds and incorporation of outside (non-TVA) expertise in many aspects of this project.  Though there are many qualified TVA personnel, non-TVA and locally based experts in the process will provide a check and balance.  Outside expertise and local expertise would need to be involved in siting the center line and low points, siting pole location and number of poles, and designing access roads among other things to minimize impacts.  Involvement by non-TVA and local expertise would also include identifying sensitive areas for special treatment, the design for sensitive areas, the vegetation removal plan, on-site planning, pre-construction review, re-clearing plan, Erosion and Sediment Control/BMP/Stormwater Control Plan, ARAP permit, and related issues.  An effective process to stop work if there are violations would also need to be delineated.   In addition, there would need to be a focus to avoid stream crossings for equipment as much as possible.

 

Local involvement would be critical to enabling TVA to facilitate efforts by local landowners to undertake restoration efforts on the affected rivers.   These efforts would compensate for the TVA line crossings by improving stream conditions within the same sub-watershed.  TVA funds to cover these projects can leverage other funds for watershed restoration.  As a result of the above comments, the costs of the proposed TVA transmission line will go up considerably to address how the proposed route would not further degrade aquatic resources.

 

If any TVA staff have any questions regarding these comments, please do not hesitate to contact me.

 

 

Sincerely,

Dorene Bolze

Executive Director

615-591-9095

Dorie@DorieBolze.com

 

         

List of Attachments sent as separate E-mails:

 

  1. HRWA Resolution of the Board, dated February 20, 2003.
  2. Memo from Synapse Energy Economics, April 1, 2002, to HRWA and Southern Alliance for Clean Energy on “Initial Findings on Transmission Planning Issues”.
  3. Report prepared by Synapse Energy Economics, April 4, 2002, The Energy Efficiency Potential in Williamson County, TN:  Opportunities for Reducing the Need for Transmission Expansion.
  4. Volunteer Site-Specific Visual Stream Assessment of 303(d)/305(b) Listed Streams in the Harpeth River Watershed:  August 2001-December 2001.  Conducted the by the HRWA.
  5. Dr. Dave Wilson, Harpeth River Watershed Sediment Study: Comprehensive Technical Report, Final Draft, 2003.